STATUS REPORT ON NEC & NLCPR


Project Under NEC

Sl. No. Name of the Project Project Cost Fund Received so Far Progress UC Submitted Target Date of Completion Balance fund to be received
Central State Total Financial Physicial Central State
1. C/o Permanent Stage-cum-Covered Gallery at Common Festival Ground, Naharlagun. 179.42 129.18 17.94 147.12 147.12 90% 82.53 30.09.2017 32.3 0.00

Project Under NLCPR

Sl. No. Name of the Project Project Cost Fund Received so Far Progress UC Submitted Target Date of Completion Balance fund to be received
Central State Total Financial Physicial Central State
1. C/o Foot Over Bridge at various location of State Capital at Itanagar, Nlg and Nirjuli AP 909.92 610.3 32.75 643.05 360.29 65% 360.29 30.09.2017 208.63 58.24
2. Development of Rangfrah Govt. Degree College at Lumbusung, Changlang A.P. 1486.46 1005.00 53.51 1058.51 1058.51 70% 535.13 31.10.2017 802.68 95.14
Total 2396.38 1615.3 86.26 1701.56 1418.8 895.42 1011.31 153.38