North Eastern Council (NEC)

Completed Projects

Data not available !

Ongoing Projects

SL No. Name of Projects Project Cost (in Lakh) Fund received (in Lakh) Remarks Details
1

C/o Permanent Stage-cum-covered Gallery at Common Festival Ground, Naharlagun.
[Components: Gallery, Prayer Hall cum Covered Gallery, Compound wall with gate, CC drain etc.]

179.42 179.42
  • Date of sanctioned : 06.11.13
  • Physical progress of work : 100%
  • UC submitted : 147.12
  • Pending UC : 32.30
  • This Central Share of Rs. 32.30 lakh was released in March’2018. File submitted to FD for concurrence and release.
2 C/o Cultural cum Development Centre at Miao.
[Components: Auditorium, Museum, Dormitory etc.]
381.54 175.50
  • Date of sanctioned : 03.04.16
  • Physical progress of work : 80%
  • UC submitted : 175.50
  • Pending UC : Nil
  • Pending installment [CS] : 206.04
  • Target date of completion : 31.07.18
Priority List of Projects

SL No. Name of Projects Amount (Rs. in Crore)
1

Construction of Solid Waste Management at Tawang [Phase-I]

15.00

2 Construction of Storm Water Drain in Doimukh township 15.00
3 Improvement of Road Network connecting ITI Dirang and Hydropower Complex including Anti-Social Erosion Works at Dirang 10.00
4
Development of Burial Ground at Kimin and Doimukh under Papum Pare District
15.00