North Eastern States Infrastructure Development Schemes (NESIDS)

Completed Projects

Data not available !

Ongoing Projects

SL No. Name of Projects Project Cost (in Lakh) Fund released (in Lakh) Progress UC Status Fund expected during 2018-19 Target Details
Central State Total Financial Physical Submitted Pending Central State
1

C/o Foot Over Bridge at various locations of State Capital of Itanagar, Naharlagun and Nirjuli in A.P.

909.92

610.30

90.99

701.29

701.29

70%

593.93

107.36 208.63 - -
2

Development of Rangfrah Govt. Degree College at Lumbusung, Changlang, A.P.

1486.46

1005.00 148.65 1153.65

1153.65

[78%]

90%

1153.65 Nil 332.81 Nil

31.07.2018

3

C/o RCC Bridge over river Dirang to connect Dirang Headquarters to Dirang township i/c Approach Road(2km) in West Kameng District , A.P.

1869.26

10.00

-

10.00

10.00

-

10.00

-

846.17

93.47

31.03.2020