Special Plan Allocation (SPA)

Completed Projects

Data not available !

Ongoing Projects

SL No. Name of Projects Project Cost (in Lakh) Fund released (in Lakh) Physical Progress Financial Progress Time line for completion of project Details
1

C/o Outdoor Stadium at Pasighat

4090.61

4085.61 80% 3880.23 31.08.2019
2

C/o Outdoor Stadium at Ziro

2431.00

2235.50 68% 2235.50

31.12.2018

3

C/o Outdoor Stadium at Yupia

5948.80 5948.80 65% 4045.00

30.09.2018

4

C/o Outdoor Stadium at Daporijo

1241.00

1096.00 90%

1096.00

15.01.2018
5

Const. of Convention Hall at Itanagar

7053.00

6546.75 100%

6546.75

31.12.2017
6

Const. of Flats for Sr. Govt. Officers  on G plus 5 Model (Phase-I) at capital Complex

7000.00 6985.00 60% 5040.00 31.12.2018
7

C/o MLA Apartment at Itanagar

13582.00

13582.00 60%

10811.00

30.09.2018
Priority List of Projects

Data not available !