Rajiv Awas Yojana (RAY)

Completed Projects

Data not available !

Ongoing Projects

SL No. Name of Projects Project Cost (in Lakh) Fund released (in Lakh) Progress UC Submitted Balance Fund to be received Details
Central State Total Financial Physical Central State
1

C/o 576 (G+3) Rental House i/c Infrastructure at Chimpu village, Itanagar

4431.20

3098.32 558.30

3656.62

3656.62 80% 3656.62 774.58 -
2

EWS Housing Project at Dirang (320 Dwelling Units)

1536.04

945.26 307.20 1252.46

1252.46

80% 1252.46 283.58 -
3

EWS Housing Project at Bomdila (384 Dwelling Units)

2037.76

1207.56 467.93 1675.49 1675.49 65%

1675.49

362.27 -
4

EWS Housing Project for C/o 256 DUs at Palin

1502.23

409.60 434.33

843.93

843.93 60% 843.93 658.30 -
  Total = 9507.23 5660.74 1767.76 7428.50 7428.50   7428.50 2078.73 -  